This is a collaborative effort between Keewatin Patricia District School Board, the Dryden Athletics Club and the community of Dryden to construct and upgrade the existing athlelic track to a modern, 4 lane, all weather IAAF standard rubberized track. The construction phases are:
Phase 1 the installation of gravel sub surface and drainage required to install phase 2. (cost $225,000)
Phase 2 the installation of ashphalt sub surface to install phase 3. (cost $ 100,000)
Phase 3 apply the ruberized surface. (cost $150,000)
Phase 1 has been awarded to Moncrief Construction Limited from Kenor and the Landscape Architect on this project is
Hilderman Thomas Frank Cram Landscape Architecture • Planning from Winnipeg
Links Below:
Concept drawing of finished track.
Putting garage in its new home. (video)
Below is photo gallery...(these are pictures of construction)